Budget vs. Forecast Section

Budget vs Forecast

Purpose

The line-bar chart shows bars for Revised Budget and Forecast. The line represents the change between Revised Budget and Forecast shown as a percentage.

The x-axis shows root-level projects. The y-axis for the bars (on the left) shows cost sheet values. The y-axis for the line (on the right) shows percentages.

The table contains columns for:

Location

  1. On the Home page, click Dashboards.
  2. Under Primavera, select Cost Sheet.
  3. On the Cost Sheet dashboard, click the Overview page.
  4. On the Overview page, expand the Budget vs. Forecast section.

Subject Area

Cost Sheet