Purpose
The line-bar chart shows bars for Original Commitments and Approved Commitment Changes. The line represents the difference between Original Commitments and Revised Commitments shown as a percentage.
The x-axis shows root-level projects. The y-axis for the bars (on the left) shows cost sheet values. The y-axis for the line (on the right) shows percentages.
The table contains columns for:
- Project Name (root-level)
- Original Commitments
- Approved Commitment Changes
- % Difference (((Approved Commitment Changes - Original Commitments) / Original Commitments) * 100)
Location
- On the Home page, click Dashboards.
- Under Primavera, select Cost Sheet.
- On the Cost Sheet dashboard, click the Overview page.
- On the Overview page, expand the Original and Revised Commitments section.