Original and Revised Commitments Section

Original and Revised Commitments

Purpose

The line-bar chart shows bars for Original Commitments and Approved Commitment Changes. The line represents the difference between Original Commitments and Revised Commitments shown as a percentage.

The x-axis shows root-level projects. The y-axis for the bars (on the left) shows cost sheet values. The y-axis for the line (on the right) shows percentages.

The table contains columns for:

Location

  1. On the Home page, click Dashboards.
  2. Under Primavera, select Cost Sheet.
  3. On the Cost Sheet dashboard, click the Overview page.
  4. On the Overview page, expand the Original and Revised Commitments section.

Subject Area

Cost Sheet