Period Actuals by Project

The pay period actuals by Resource page of the Resource Analysis Dashboard

Purpose

The Period Actuals by Project section displays the actuals units for each activity performed by a resource in a project. The table provides a snapshot of the resource's history over past periods.

Location

  1. On the Home page, click Dashboards.
  2. Under Primavera, select Resource Analysis.
  3. On the Resource Analysis dashboard, click the Period Actuals page.
  4. Expand the Period Actuals by Project section.

Subject Area

Resource Period Actuals