6000000000004000 - PDB 90% Full

The PDB on the EPAP has exceeded 90% of purchased capacity.

Recovery

  1. Log in to the EPAP CLI as epapdev.
  2. Use the manageLicenseInfo utility to check the value of purchased capacity (see the "Current license capacity"):
    $ manageLicenseInfo –l
  3. Purchase additional provisioning database capacity licenses as needed.
  4. Use the manageLicenseInfo utility to specify the additional amount of desired PDB capacity, where "License Capacity value" is the number of additional licenses required when one license supports 0.5M data (DN, IMSI, and IMEI):
    $ manageLicenseInfo –a <License Capacity value>

For assistance or additional information, contact My Oracle Support (MOS).