Delay Amount Section

Delay Amount Section of the Schedule Health Page-

The Delay Amount section of the Schedule Health page displays the planned duration of the project (solid blue color) as well as the predicted duration which can represent either a delay or early finish (striated red color). The predicted duration is calculated with a 10% probability and an 80% probability.

In the above example, the Haitang Corporate Park project has a Planned Duration of 521 days. The Predicted Duration with a 20% probability of delay is 526 days that includes a delay of 5 days whereas the Predicted Duration with an 80% probability of delay of 718 days, with a predicted delay of 197 days.

Note: If there is no delay (zero), then the planned duration is identical to the predicted duration of the project.

Related Topics

Schedule Health Page

Chance of delay on this project Section

Schedule Assessment Metrics

Factors Considered in Predicting Project Delay Section

Activities with the Largest Predicted Delay Section

Compare this Project Section



Legal Notices | Your Privacy Rights
Copyright © 2021

Last Published Friday, February 12, 2021