Activity Information
The Activity Information tab of the Activity Details pane provides detailed information about each activity in a WBS. To access the pane, select an activity in a WBS (rectangle) on the heatmap to view its related activities.
It includes the following sections:
Overview Section: Provides a synopsis of the current state of each activity.
- WBS Name: The name of the WBS element
- Activity ID: The unique identifier of the activity.
- WBS Code:The unique identifier of the WBS for the associated activity.
- Predicted Delay: The number of days that an activity will be delayed, predicted by CIC Advisor.
- Delay Probability: The likelihood of the activity being delayed.
- Actual Delay: The number of days the activity will actually be delayed.
- Activity Completion: The percent of the activity that has been completed.
- Successors: The number of activities required to start or finish after an activity in the activity relationship has started or finished, depending on the relationship type.
- Predecessors: The number of activities required to start or finish before an activity in the activity relationship starts or finishes, depending on the relationship type.
- Activity Status: The current condition of the activity.
- Primary Resource: The person primarily responsible for performing or overseeing work related to a specific activity or assignment.
Schedule Section: Provides project schedule information related to each activity.
- Planned Start: The date the activity is scheduled to start.
- Planned Finish: The date the activity is scheduled to finish if the activity has not started.
- Baseline Planned Start Date: The planned start date for the activity as is set in the current baseline.
- Baseline Planned Finish Date: The planned finish date for the activity as is set in the current baseline.
- Planned Duration: The total working time from the project planned start date to the planned finish date.
- Predicted Finish Date: The date that an activity will be completed, predicted by CIC Advisor.
- Free Float: The amount of time the activity can be delayed before delaying the start date of any successor activity.
- Actual Duration: The total working time from the activity Actual Start date to the Actual Finish date for completed activities, or the total working time from the Actual Start date to the data date for in-progress activities. The actual working time is computed using the activity's calendar.
- Total Float: The amount of time the activity can be delayed before risking a delay to the project finish date.