Assign a risk to an activity to explicitly identify the activity impacted by the risk.
You can assign a risk to an activity while you are adding project risks on the Risks page or while managing your activities on the Activities page.
To assign a risk to an activity from the Risks page:
- Click Projects.
- On the Projects navigation bar, click Risks.
- On the Risks page, click a risk.
- Click the Activities detail window and click Assign....
- In the Select Activity dialog box:
- Select one or more activities and click Select.
- On the Risks page, click Save.
To assign a risk to an activity from the Activities page:
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page, select the activity you want to assign a risk.
- On the Risks detail window, click Assign....
- In the Select Risk dialog box select a risk and click Assign.
- On the Activities page, click Save.