Configuring Activity View Gantt Chart

Configure Gantt chart options to determine how the chart will display.

To configure Gantt chart options:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page:
    1. Click Customize View.
    2. In the Manage View dialog box, click the Gantt tab.
    3. On the Gantt tab:
      • Select the Data date line option to show the data date on the Gantt.
      • Select the Relationship lines option to show lines between activities on the Gantt.
      • Select the Non-driving relationships option to draw lines between activities on the Gantt even where the relationship doesn't affect the successor's dates.
      • Select the Sight Lines option to show vertical lines between each segment of the timescale.
      • Select the Non-work time shading option to have non-work time shaded on the Gantt.
      • Select a Timescale.
    4. Click Apply.

Tips

Related Topics

Configuring Activity Views

Configuring Activity View Columns

Configuring Activity View Grouping

Configuring Activity View Gantt Chart Bars

Configuring Activity Network

Configuring Activity View Access

Converting Classic Views to Standard Views



Legal Notices | Your Privacy Rights
Copyright © 1999, 2021

Last Published Monday, December 6, 2021