Configuring Project Calendars

Perform the following tasks when creating or updating a project calendar:

Related Topics

Assigning a Base Calendar to a Project Calendar

Setting Work Hours Per Period for a Project Calendar

Configuring the Standard Work Week for Project Calendars

Modifying Calendar Days on Project Calendars

Changing a Project Calendar to a Global Calendar



Legal Notices | Your Privacy Rights
Copyright © 1999, 2021

Last Published Monday, December 6, 2021