When viewing the Resource Usage Spreadsheet for a specific project, you can filter the activities displayed in the Activity Table, Gantt Chart, Activity Usage Spreadsheet, or Activity Network, so that they correspond to the resource information currently displayed in the Resource Usage Spreadsheet.
- To display only the activities to which a specific resource has been assigned, in the left pane of the bottom layout select the resource, then, in the Display Activities for Selected section, mark the Resource checkbox.
- To display specific activities for a resource, in the left pane of the bottom layout select the resource, then, in the middle pane of the bottom layout, select one or more of the resource's activity assignments. In the Display Activities for Selected section, mark the Assignments checkbox.