View a spreadsheet of resource overallocation across all projects

You can choose Resource Usage Spreadsheet fields to spread overallocated resources units over early and late dates.

  1. In the Activities window, choose View, Show on Bottom, Resource Usage Spreadsheet.

    You can also click the Layout Options bar, then choose Show on Bottom, Resource Usage Spreadsheet.
  2. In the right pane of the bottom layout window, click the Display Options bar and choose Show All Projects, if it is not already selected. A check next to Show All Projects indicates that it is selected.
  3. Right-click in the spreadsheet, then choose Spreadsheet Fields, Customize. Select Overallocated Early Units and/or Overallocated Late units in the available options section, then click the right arrow to add the fields to the spreadsheet.

    When a resource is spread over the early dates of activities, to view the number of units beyond the resource's limit that are planned over a given timeperiod, select Overallocated Early Units.

    When a resource is spread over the late dates of activities, to view the number of units beyond the resource's limit that are planned over a given timeperiod, select Overallocated Late Units.
  4. Click Ok.