Description: The list of all CBS codes defined at the workspace level part of a Workspace CBS
Field | Type | Description | Read-Only |
---|---|---|---|
actualCostToDate | Double | The actual costs incurred on the scope assignment. This tracks the VOWD (Value of Work Done). | Yes |
actualHoursToDate | Double | The actual hours spent on the scope assignment. This tracks the VOWD (Value of Work Done). This is the cumulative value for all objects in the workspace with the same CBS code. | Yes |
adjustedCost | Double | The amount the scope assignment work that is not yet accounted for. For example, you might enter a value to represent pending change requests that are likely to be approved. | Yes |
approvedChangedCost | Double | The sum of all approved cost changes in the change records for the scope assignment. | Yes |
approvedChangedHours | Double | The sum of all approved change hours in the change and transfer records for the scope assignment. This is the cumulative value for all objects in the workspace with the same CBS code. | Yes |
atCompletionCost | Double | The total cost at the completion of the scope assignment.Calculated as Revised Cost plus Adjusted Cost. | Yes |
atCompletionHours | Double | The total hours expected for the scope assignment.Calculated as Revised Hours plus Adjusted Hours. This is the cumulative value for all objects in the workspace with the same CBS code. | Yes |
bacCost | Double | The Revised Cost or At Completion Cost at the time the current baseline was set, depending on the selection for the Budget at Completion Method. The Revised Cost of the current project if no baseline is set. | Yes |
bacHours | Double | The Revised Hours or At Completion Hours at the time the current baseline was set. This is the cumulative value for all objects in the workspace with the same CBS code. | Yes |
baselineCost | Double | The Revised Cost at the time the current baseline was set. | Yes |
baselineHours | Double | The Revised Hours at the time the baseline was set. This is the cumulative value for all objects in the workspace with the same CBS code. | Yes |
cbsCode | String | The code value of the CBS code. The code may have one or more segments according to the segment definition. | No |
cbsTemplateCodeId | String | The unique ID generated by the system. | No |
cbsTemplateId | ForeignKey | The unique identifier of the CBSTemplateCode. | Yes |
copiedFromItemId | ForeignKey | The unique identifier of the CBSTemplateCode. | No |
costType | Enum | The category of the cost breakdown structure code. Expense: Represents an expense. Capital: Represents capital. None: Type is not divided into expense or capital.None is selected by default if no other choice is made. | No |
currentBudget | Double | The total approved current manual budget of a project. Calculated as the sum of Approved Original Manual Budget plus Approved Manual Budget Changes plus Approved Manual Budget Transfers. | Yes |
currentBudgetWorkspace1 | Double | Workspace current budget. | Yes |
currentBudgetWorkspace2 | Double | Workspace current budget. | Yes |
currentBudgetWorkspace3 | Double | Workspace current budget. | Yes |
description | String | The name of the CBS Code. | No |
eacCost | Double | Calculated as ETC Cost plus Actual Cost to Date. | Yes |
eacHours | Double | Calculated as ETC Hours plus Actual Hours to Date. This is the cumulative value for all objects in the workspace with the same CBS code. | Yes |
earnedCost | Double | Calculated as Performance Percent Complete multiplied by BAC Cost. | Yes |
earnedHours | Double | Calculated as Performance Percent Complete multiplied by BAC Hours. This is the cumulative value for all objects in the workspace with the same CBS code. | Yes |
etcAdjustedHours | Double | The amount of scope assignment work that is not yet accounted for. This is the cumulative value for all objects in the workspace with the same CBS code. | Yes |
etcCost | Double | The estimate of the cost needed to complete the work.Calculated as BAC Cost minus Earned Cost. | Yes |
etcHours | Double | The estimated number of hours needed to complete the work. Calculated as BAC Hours minus Earned Hours. This is the cumulative value for all objects in the workspace with the same CBS code. | Yes |
installedCost | Double | The total cost incurred on the scope assignment as of the current date. | Yes |
installedHours | Double | Hours spent on the scope assignment. Calculated as Installed Quantity multiplied by Revised Productivity Rate. This is the cumulative value for all objects in the workspace with the same CBS code. | Yes |
isActive | Boolean | The active field indicates whether the CBS code is active for use. | No |
isCodeCopied | Boolean | The flag represents is templateCode copied or not | No |
isTotalRow | Boolean | Indicates this item represents the total cost of the project. | Yes |
parentId | ForeignKey | The unique identifier of the parent CBS. | No |
pendingChangedCost | Double | The unique identifier of the parent CBS. | Yes |
pendingChangedHours | Double | Calculated as the sum of all pending cost changes in the change records for the scope assignment. | Yes |
plannedHours | Double | Calculated as the sum of all pending hour changes in the change records for the scope assignment. This is the cumulative value for all objects in the workspace with the same CBS code. | Yes |
projectActualCost | Double | Total cost accrued on a project within a given time period. The Actual Cost data is only available when the application is connected with P6 EPPM and is not editable. | Yes |
projectActualHours | Double | The actual hours spent on the scope assignment. This tracks the VOWD (Value of Work Done). | Yes |
projectCPI | String | The measure of a project's cost efficiency. A value of less than 1 indicates the project is over budget, while a value greater than 1 indicates the project is under budget. | Yes |
projectEarnedCost | Double | The value of work performed on a project in reference to the approved budget for the project. The cost value used for the Earned Value Management of a project. | Yes |
projectEarnedHours | Double | Calculated as Performance Percent Complete multiplied by BAC Hours. | Yes |
projectHPI | Double | Calculated as the total of Project Earned Hours divided by Project Actual Hours. | Yes |
pushDownStatus | Boolean | The push down status of a cbs template code. May be manual or automatic. | No |
remainingCost | Double | The amount left to be spent.If Rate By set to Hours, then Remaining Cost equals Remaining Hours multiplied by Revised Cost Rate.If Rate By set to Quantity, then Remaining Cost equals Remaining Quantity multiplied by Revised Cost Rate. | Yes |
remainingHours | Double | The number of hours left for the scope assignment. Calculated as Remaining Quantity multiplied by Revised Productivity Rate. This is the cumulative value for all objects in the workspace with the same CBS code. | Yes |
revisedCost | Double | The Original Cost before the baseline is set. After the baseline is set, Revised Cost equals Original Cost plus Approved Change Cost. | Yes |
revisedHours | Double | Original Hours before the baseline is set. After the baseline is set, Revised Hours is equal to Original Hours plus Approved Change Hours. This is the cumulative value for all objects in the workspace with the same CBS code. | Yes |
sequenceNumber | String | The CBS template item sequence number. | Yes |
workspaceCode | String | The user-specified identifier of the workspace. | Yes |
workspaceId | String | The unique identifier for the workspace.The workspace object can also be identified by its unique criteria. | No |