Running Send Primavera Cloud project data to P6 for Task Synchronization

To send project data with lean task information from Primavera Cloud to P6 EPPM:

Prerequisites

Procedure

To send the minimal required project data from Primavera Cloud to P6 EPPM:

  1. Sign in to Gateway as an administrator or user.
  2. In the sidebar, select Synchronizations.
  3. In the Synchronization Name column, select Send Primavera Cloud Project data to p6 for Lean Task, and then select Edit....
    1. From the Source list, select the Primavera Cloud deployment where your source data resides.
    2. From the Destination list, select the P6 deployment where your data is to be sent.
    3. Select Next.
    4. Select projects in the Primavera Cloud Project Filter field as follows:
      1. From the Fields list, select Project Ids.

        You can also select projects using Lookup in Primavera Cloud, Workspace Ids, Project Code Type Name, Project Code or Project Status.

        If you chose Lookup in Primavera Cloud, see Searching Projects in Source Deployments.

      2. In the Value field, enter the project ID whose project data is to be sent to P6 EPPM.
    5. In the EPS Location field, enter the EPS ID where the project data from Primavera Cloud is to be located within P6 EPPM.

      Note: If the project in Primavera Cloud is already associated with an EPS code, and you now enter a different EPS code for this parameter in Gateway, then the EPS code assigned in Primavera Cloud takes precedence when you run this synchronization.

    6. Select Save to exit the wizard.
  4. On the Synchronizations page, select Run.
  5. In the sidebar, select Monitoring.
  6. Select the job number of this synchronization and confirm the Status displays Completed.


Legal Notices | Your Privacy Rights
Copyright © 2019 2021

Last Published Monday, November 8, 2021