Sending P6 Project data to Primavera Cloud for Schedule Assessment

If you want to send P6 project data for schedule assessment in Primavera Cloud, then activity, calendar, activity relationship, resource, resource assignment, role and WBS data must be transferred from P6.

To send P6 project data with schedule information, complete the following sequence:

  1. Common Prerequisites
  2. Creating a Project with Schedule Information in P6 EPPM
  3. Running Send P6 project data to Primavera Cloud for Schedule Synchronization using Gateway
  4. Verifying the Transferred Project in Primavera Cloud

You can also watch a this video on how to Send P6 Schedule Data to Primavera Cloud



Legal Notices | Your Privacy Rights
Copyright © 2019 2021

Last Published Monday, November 8, 2021