Creating a Project with Schedule Information in P6 EPPM

To create a project with schedule information:

  1. Sign in to P6 EPPM as a administrator or a user.
  2. In the Projects menu, select Open Projects select an EPS.
  3. In the EPS page, expand an EPS node and select a project.
    1. In the General detail window, confirm the information for the project.
  4. In the Activities page, add activities for the project and calendar dates for each activity.
    1. In the Activities page, add activities for the project and calendar dates for each activity.
    2. In the Assignments detail window add resource, resource assignment, role for each activity.
    3. In the Relationships details window define the sequence of activities in the project.
  5. In the Risks page, develop a risk response plan and a risk response action plan, risk details, and generate a probability and impact diagram.
  6. Select Save.