This is a mandatory project data field mapping template which must be included in the business flow to transfer summary data from P6 to Unifier. However, this template is not mandatory for Send Activity data from P6 to Unifier business flow. Use this template to establish a link between a Unifier and P6 projects. This template creates a new project in Unifier. .
The following fields are mapped:
Unifier | Gateway | P6 |
---|---|---|
data_date | DataDate | DataDate |
ProjectNumber | Id | Id |
ProjectName | Name | Name |
uuu_shell_status | Status | Status |
uuu_project_start_date | StartDate | StartDate |
uuu_int_schedule_type | ProjectScheduleType | ProjectScheduleType |
uuu_int_internal_proj_id | InternalProjectId | ObjectId |