This project data field mapping template synchronizes Project data from P6 to Unifier. This field mapping template is used in the Get Activities and Assignments data from P6 for EVM business flow. The following fields are mapped:
Unifier | Gateway | P6 |
---|---|---|
data_date | DataDate | DataDate |
ProjectNumber | Id | Id |
ProjectName | Name | Name |
uuu_shell_status | Status | Status |
uuu_project_start_date | StartDate | StartDate |
uuu_int_schedule_type | ProjectScheduleType | ProjectScheduleType |
uuu_P6ETCUserValue | EarnedValueETCUserValue | EarnedValueETCUserValue |
uuu_P6ETCComputeType | EarnedValueETCComputeType | EarnedValueETCComputeType |