Company Cost Sheet Data Sources
Data Source | Description |
---|---|
Single Sources | Data from single data sources Project Cost1 to Project Cost25 is rolled up from project-level cost sheets. Users can also view data sources based on business process data rolled up from the project level. |
Business Process (All statuses) | Included in the Single Sources list are all Cost BPs that are available for your project, and all their terminal statuses. |
AFC | Allowance for Change. This is a contingency value. |
Funded Records | This column shows records in which the CBS code is funded, that is, spend-type business process records that consume funds. |
Unfunded Records | This corresponds to spend-type BP records that are not funded. |
Prior Forecasts | Prior forecasts |
Yet To Buy |
This is a portion of a commit that you still need to buy. This can be automated for BPs (commit BPs can track YTB). In Cost Properties, you must set "Auto" "Transaction" options, which track YTB. |
Project Cost 1 to Project Cost 25 | Roll up from all projects |
All Project Single Sources | All other data sources are similar to Project Cost Sheet. |
Logical Sources | These sources are formulas. |
Company Budget Remaining Balance | This is a place holder for a formula you create (optional). |
Company Budget Variance | This is a place holder for a formula you create (optional). |
Company Commits | Can be used for company commit BPs |
Company Forecasts | This is a place holder for a formula you create (optional). |
Company Forecasts (Unaccepted) | This is a place holder for a formula you create (optional). |
Company Forecasts Variance | This is a place holder for a formula you create (optional). |
Company Funding | You can roll up all project funding here. |
Company Spends | You can roll up spends BPs here. |
Company CBS Funding | This requires additional setting in Funding Sheet; see Setting Up the Funding Manager. |
Company Manual Funding by CBS |
|
Company Cost 1-25 |
|