Manual Activity Sheet Categories

There are three categories of Activity Sheet:

Duration Based Schedules

The Duration Based Schedules are schedules in which you use P6 to capture only “durations” of the schedules. Users define the CBS structure, Activities, Start / End Dates of Activities, Durations, and so forth, but you do not do Resource Assignments or Cost management in P6.

Cost Loaded Schedules

Users use P6 to capture CBS structure, activities, durations, resource assignments, as well costs.

The Activity Sheet, in this case, receives costs as well as dates that come from P6.

Resource Loaded Schedules

Users use P6 to capture “durations” as well as resource assignments (resource units, resource CBS assignment, resource units spread, actual resources consumed till date, and so on). There are no costs captured within P6. A manual activity Sheet, in this case, can receive all the resource units and calculate costs using P6 data and rates.

See Also

Activity Manager

Activity Sheet Sub-Node

Creating a Manual Activity Sheet

Importing Manual Activity Sheet

Creating a WBS Sheet

Manual Activity Sheet

Bulk Assigning WBS Code to Different Activities

Link Activities (Adding Dependencies)

Manual Activity Sheet Gear Menu

Manual Activity Sheet Start Date, Finish Date, and Duration

Manual Activity Sheet and CSV Template

Manual Activity Sheet (Schedule Types)

Manual Activity Sheet Dates

Activity Sheet User Defined Report (UDR)

Creating and Managing Views in Activity Sheets and the System Activity Sheet



Last Published Monday, April 14, 2025