Publishing Process for P6 Projects

Before running the ETL process in CIC Analytics, P6 EPPM projects must be loaded into P6 Extended Schema.

To load P6 EPPM projects to P6 Extended Schema, complete the following tasks:

  1. Configuring P6 EPPM Publication Services Settings
  2. Enabling Automatic Publishing of P6 Global Data or Manually Publishing P6 Global Data
  3. Enabling Automatic Publishing of P6 Project Data or Manually Publishing P6 Project Data

Related Topics

P6 EPPM Publication Services Overview

Configuring P6 EPPM Publication Services Settings

Enabling Automatic Publishing of P6 Global Data

Enabling Automatic Publishing of P6 Project Data

Manually Publishing P6 Global Data

Manually Publishing P6 Project Data