Allocating Units by Spreading Units Across a Time Period

When planning resource allocation for a project, you can use the spreadsheet to spread work units evenly across a selected time period.

To spread units across a time period:

  1. Click Resources.
  2. On the Resources navigation bar, click Planning.
  3. Expand a project and click the resource or role for which you want to allocate units.
  4. Select the time period to spread units.
    • To specify start and finish dates, click the Start Date and Finish Date fields and select the dates from the calendar.
    • To spread units between the Project Forecast Start and the Forecast Finish date of the project, select Life of Project.
  5. Click the Total Units field and enter the number of units to spread between the Start and Finish dates you selected.
  6. On the Actions menu, select Synchronize Resources.
  7. Click Save.

Tips

Related Topics

Resource Planning

About Resource Planning

Assigning Resources or Roles to Projects or WBS Elements

Searching for a Resource to Assign

Assigning Projects or WBS Elements to Resources or Roles

Allocating Units to Resources or Roles

Splitting Resource Assignments

Exporting the Planning Spreadsheet



Legal Notices | Your Privacy Rights
Copyright © 1999, 2024

Last Published Thursday, July 25, 2024