During your planning, you might find that some resources become overloaded with work. One way to resolve overallocation of units to a resource is to assign some of its total units to another resource.
To split resource assignments:
- Click Resources.
- On the Resources navigation bar, click Planning.
- For the overloaded resource, select Row Actions menu, select Split Resource Assignments.
- In the Split Resource Assignments dialog box
- Select a resource from the list.
- In the Percentage allocation to new Resource field, enter a percentage of the original resource's total units to re-assign.
- Click Assign.