Overview
Use this page to add, modify, or delete project risks.
Note: If the Probability, Schedule, and Cost fields are disabled, a risk scoring matrix is not assigned to the current project. You can still enter risk data on this page; however, a risk scoring matrix must be assigned to a project to perform qualitative risk analysis.
Screen Elements
Add button
Adds an item to the table.
Expand All
Enables you to see all of the items in a hierarchical list.
Collapse All
Enables you to hide subordinate items in a hierarchical list.
Full Screen
Expands the current work area so it fills the entire display.
Prints the Grid View.
Customize View
Opens the Customize View dialog box.
Search
Enables you to perform a search based on the value you enter in the search bar.
Risk Table
ID field
The unique identifier for the risk.
Name field
The name for a particular type of risk classification.
Type list
Determines whether a risk is a threat or an opportunity.
A threat will have a negative impact on your project, while an opportunity can have a perceived benefit to the project.
Status field
The current state of the risk.
Proposed: The risk is identified and awaits approval.
Open: The risk is approved as a valid risk to the project.
Active: The risk is currently impacting the project.
Rejected (Closed): The risk is not seen as a valid risk to the project and therefore will not be tracked and managed by the project. The data for this risk cannot be modified once it is closed.
Managed (Closed): The risk occurred and was successfully managed by the project team and is no longer an active risk. The data for this risk cannot be modified once it is closed.
Impacted (Closed): The risk occurred, impacted the project and is no longer an active risk. The data for this risk cannot be modified once it is closed.
Owner field
The resource who has ownership of the risk.
Probability field
The probability of the risk occurring.
Schedule field
The impact on the schedule if the risk occurs.
Cost field
The monetary impact on the project if the risk occurs.
Score field
The risk calculation based on the values defined for probability, cost impact, schedule impact, and any additional user-defined impacts for the risk.
Response Total Cost field
The total cost of the active response plan.
If a response plan is active, this field is disabled and displays the sum of the Remaining Cost plus Actual Cost fields for all response action items in the response plan. Rejected response action items are not included in the calculation.
risk table
Download
Enables you to download the view as an Excel file. For hierarchical data, the top level and any expanded levels are downloaded. For flat lists, all rows are downloaded.
Collapse Dock
Collapses the dock.
Show/Hide Tabs
Enables you to configure which tabs are shown and hidden.
Previous Record button
Shows the previous record.
Previous Record button
Advances to the next record.
Risks Page detail windows:
Codes Detail Window of the Risks Page
Response Plans Detail Window of the Risks Page
Activities Detail Window of the Risks Page
Risk Details Window of the Risks Page
Probability and Impact Diagram Detail Window of the Risks Page
UDF Detail Window of the Risks Page
Getting Here
- Click Projects.
- On the Projects navigation bar, click Risks.