Configure grouping options to define how fields are grouped on the EPS page.
To configure EPS view grouping:
- Click Projects.
- On the Projects navigation bar, click EPS.
- On the EPS page:
- Click the Views list and select a view.
- Click Customize View.
- In the Customize View dialog box, click the Grouping tab.
- On the Grouping tab, configure the grouping options and click OK.
- Click Save and Apply.
Tips
- When activities are grouped, the Gantt chart displays a summary bar for each group. The summary bar represents the time period from the earliest Start to the latest Finish for the group.
- Use the To Level list to select the number of hierarchy levels when grouping by a hierarchical field. When grouping by dates, use the To Level list to select a time interval.
- The band color you select will be displayed in the table.
- Grouping bands are displayed by default when you group by a project code or EPS even if the bands are empty. Select the Hide if empty option in the Customize View or Customize Groupings dialog boxes to remove these bands from view.
- Empty bands are hidden, even if the Hide if empty option is not selected, when the view is grouped by multiple data items and one of the data items is hierarchical.
- You can also access the grouping options by selecting
Group... on the View
menu.