Assign yourself to assignments of activities with existing unstaffed roles that match your role.
To staff yourself to a role assignment:
- Select Timesheets
- Select Actions, and then select Staff Role Assignments.
- In the Staff Role Assignments dialog box:
- Select the project.
- Select one or more activities.
- Select Assign & Add to assign your role to the activities and add the activities to your timesheet, or Assign to assign your role to the activities without adding them to your timesheet.
Tips:
- A project-level setting determines whether a project is listed so you can assign yourself to its activities. If you need to assign yourself to a project that is not listed, contact your project manager or P6 administrator.