Assign your resource to an activity so that you can add the activity to a timesheet.
- Select Timesheets
- Select Actions, Assign Activity.
- In the Assign Activities box:
- Select the project you want to assign yourself to.
A project-level setting determines whether a project is listed so you can assign yourself to its activities. If you need to assign yourself to a project that is not listed, contact your project manager or P6 administrator.
- Select one or more activities.
Note: You can filter the list of activities by selecting Activity Name, Activity ID, Role Assigned, or Proficiency in the Search list, entering text in the for box and selecting Go.
- Select Assign & Add to assign your resource to the activities and add the activities to your timesheet, or Assign to assign your resource to the activities without adding them to your timesheet.
- Select the project you want to assign yourself to.