Troubleshooting - Future period bucket planning FAQ

Why are some future period buckets gray/uneditable?

When a future period bucket is not eligible for editing, the spreadsheet cell is gray.

Spreadsheet cells are gray/uneditable when any of the following are true:

Why can't I enter different values for the Budgeted or Planned and Remaining Units fields?

For activities that have not started, if the project-level setting 'Link Budgeted or Planned and At Completion for not started activities' is marked (Project Details, Calculations tab), the total planned values of the Budgeted or Planned Units and Remaining (Early) Units for the assignment will always be equal. For example, when you enter a value for a future period in the Budgeted or Planned Units field, the Remaining (Early) Units field is automatically populated with the same value; the reverse is also true. If this setting is not marked, you can enter different values for the same future period in the Budgeted or Planned Units and Remaining (Early) Units fields; in this case, the total values for each field are calculated independently for the assignment.

 

For activities that are in progress, you can always enter different future period values in the Budgeted or Planned Units and Remaining (Early) Units fields.

Why did the manual future period values I entered change?

There are many reasons why the future period values you entered for an assignment might change to different values or be placed in a different timeperiod. For example, remaining unit data for an assignment might change when you apply actuals, or if you entered values in daily increments and changed the timescale to a larger increment (for example, days to weeks), the data you see is a roll-up of the daily values you entered.

More specifically, changes to some activity or assignment data can cause the manual future period values to be respread and, in some cases, recalculated. When you manually enter data in future period buckets, the bucket values are stored in the database. When you modify activity or assignment information that causes the values to respread across future period buckets, the values stored in the database do not change; only the spread of those values across future period buckets changes. When you modify activity or assignment data that causes the values to be recalculated, the values you originally entered are recalculated according to the manual distribution and stored in the database; the original values are lost.

The sections below detail the activity and assignment fields that may cause manual future period values to be respread or recalculated.

Changing values in the following ASSIGNMENT-related fields may respread manual future period values across buckets:

Note:

Do application settings for linking costs and units affect manual future period values?.

Note

When you manually edit future period units and costs for an assignment (for example, you change the Remaining Cost of the assignment), the following will occur depending on the values of these settings:

Changing values in the following activity-related fields may respread manual future period values across buckets:

Notes

Adding a resource assignment to an activity that has an existing resource assignment

Adding a resource assignment to an activity that has an existing role assignment, or vice versa

Changing values in the following ASSIGNMENT-related fields may RECALCULATE manual future period values:

Changing values in the following ACTIVITY-related fields may RECALCULATE manual future period values:

Related Topics

Add a resource

Add a role

Change Resources tab columns

Select calculation options for resource and role assignments



Legal Notices | Your Privacy Rights