Getting Started - Future period bucket planning FAQ

Where can I manually enter future period values?

You can manually enter future period values for an assignment in the Budgeted Units or Planned Units and Remaining (Early) Units fields in the Resource Usage Spreadsheet in the Resource Assignments and Activities windows.

Note

Can I enter future period values for all assignments to activities?

No. You can manually enter future period values for assignments when:

For more information on these and other future period bucket planning restrictions, see the next question below.

Why are some future period buckets gray/uneditable?

When a future period bucket is not eligible for manual future period bucket planning, the spreadsheet cell is gray.

Spreadsheet cells are gray/uneditable when:

Can I enter values in any time unit?

The values you enter in the Budgeted or Planned Units and Remaining (Early) Units fields are converted to the Unit/Time specified in the User Preferences, Time Units tab. For example, if the Unit/Time user preference is set to Hour and you enter 1d, the value is converted to 8h. To avoid planning mistakes, you should set the Unit/Time user preference to the same time unit you use to plan your work. For example, if you plan your work in hours, set the Unit/Time to Hours.

Can I manually enter or edit values for Remaining Late Units?

No, you can only enter or edit values for budgeted or planned Units and Remaining (Early) Units.