Enter multiple resource prices over time

  1. Choose Enterprise, Resources.
  2. Select the resource whose prices you want to enter.
  3. Click the Units & Prices tab.
  4. Repeat the following to assign dates with different price/units to the resource:
    1. Click Add.
    2. To change the price's effective date, double-click the Effective Date field, click , then select a new date.
    3. Type the maximum number of time units the resource can perform, followed by a forward slash (/) and the appropriate time duration.

      For example, if the selected resource is one person, a reasonable value may be 8 hours (units) per day (duration). In this case, the Max Units/Time would be 8.00h/ d, or 8 hours of work per day. Similarly, if the selected resource is a department with 5 people, then the Max Units/Time may be 40.00h/ d. This means that 5 people can perform 40 hours of work per day, rather than 1 person performing 8 hours of work per day.
    4. Double-click the Price/Unit field, then type the resource's monetary price. For labor resources, indicate the time unit with a forward slash (/) and the appropriate time unit abbreviation, such as $50.00/h (for 50 dollars per hour).

      Right-click in the Units & Prices table and select Customize Resource Rate Columns to add or remove additional price/unit fields.

When P6 Professional is connected to a P6 Professional database, these fields display the name defined for the rate types in the Rate Types tab in the Admin Preferences dialog box.

When P6 Professional is connected to a P6 EPPM database, these fields display the name defined for the rate types from the Application Settings in P6.