Shortening the critical path

The critical path is a series of activities that determines a project's completion time. The duration of the activities on the critical path controls the duration of the entire project; a delay to any of these activities will delay the finish date of the entire project. Critical activities are defined by either the total float or the longest path in the project network.

To shorten the duration of a project, focus on the critical path. Filter the critical activities and make any of the following adjustments:

Activities can appear critical without being on the critical path, if they are part of an open-ended chain. To make these activities appear noncritical, so that you can focus on the critical path, choose Tools, Schedule. On the General tab, clear the Make Open-Ended Activities Critical checkbox.