Define critical activities

When you schedule your project, you can decide how you want to identify the critical activities.

  1. Choose Tools, Schedule.
  2. Click Options.
  3. In the General tab, select an option to determine the method for defining critical activities.

    If you choose Total Float less than or equal to, specify the maximum float time for activities before they are marked critical. You can type a new number and time unit.

    If you choose Longest Path, the activities on the longest path in the network are considered critical. In a multicalendar project, the longest path is calculated by identifying the activities that have an early finish equal to the latest calculated early finish for the project and tracing all driving relationships for those activities back to the project start date.

Note

Related Topics

Calculate multiple float paths