CBSDurationSummary

Description: Create/Update Duration Based Summary Sheet in Unifier.

Field

Type

Description

Read-Only

ActualDuration

Double

Actual Duration of work done for a CBS code

No

ActualFinish

DateTime

Actual date when work gets finished for a CBS code

No

ActualStart

DateTime

Actual date when work gets started for a CBS code

No

BaselineType

String

Baseline type of the associated baseline

No

bitemid

ForeignKey

CBS code id

No

DataDate

DateTime

Progress As Of Date

No

ElementId

String

The unique identifier of the Duration Summary.

No

OriginalProjectId

Int

The original Project id for a baseline project

No

PercentComplete

Double

Percentage of total work completed for a CBS code

No

PlannedDuration

Double

Planned Duration of work related to a CBS code

No

PlannedFinish

DateTime

Planned date for work to get finished for a CBS code

No

PlannedStart

DateTime

Planned date for work to get started for a CBS code

No

ProjectNumber

ForeignKey

Project id

No

RemainingDuration

Double

Remaining Duration of work related to a CBS code

No

RemainingFinish

DateTime

Date when Remaining work would finish for a CBS code

No

RemainingStart

DateTime

Date when Remaining work would get started for a CBS code

No

Title

String

Project Title

No