CBSExpenseSpread

Description: Summarized spread data per CBS per expense category.

Field

Type

Description

Read-Only

ActualCost

Double

Actual Cost for a CBS-Expense combination on a date within Actual Duration

No

ActualUnits

Double

Actual Units for a CBS-Expense combination on a date within Actual Duration

No

AtCompletionCost

Double

At Completion Cost for a CBS-Expense combination on a date within At Completion Duration

No

AtCompletionUnits

Double

At Completion Units for a CBS-Expense combination on a date within At Completion Duration

No

BaselineType

String

Baseline type of the associated baseline

No

bitemid

ForeignKey

CBS code id.

No

DataDate

DateTime

Progress As Of date

No

ElementId

String

The unique ID generated by the system.

No

EndDate

DateTime

At Completion End date

No

ExpenseCategory

String

Expense Category viz. Equipment, Travel, Facilities, etc.

No

OriginalProjectId

Int

The original Project id of a baseline Project

No

PlannedCost

Double

Planned Cost for a CBS-Expense combination on a date within Planned Duration

No

PlannedUnits

Double

Planned Units for a CBS-Expense combination on a date within Planned Duration

No

ProjectId

String

Project short name

No

ProjectNumber

ForeignKey

The unique Project Number.

No

RemainingCost

Double

Remaining Cost for a CBS-Expense combination on a date within Remaining Duration

No

RemainingUnits

Double

Remaining Units for a CBS-Expense combination on a date within Remaining Duration

No

StartDate

DateTime

At completion Start date

No

SummaryActualCost

Double

Actual Cost for a CBS-Expense combination

No

SummaryActualUnits

Double

Actual Units for a CBS-Expense combination

No

SummaryAtCompletionCost

Double

At Completion Cost for a CBS-Expense combination

No

SummaryAtCompletionUnits

Double

At Completion Units for a CBS-Expense combination

No

SummaryPlannedCost

Double

Planned Cost for a CBS-Expense combination

No

SummaryPlannedUnits

Double

Planned Units for a CBS-Expense combination

No

SummaryRemainingCost

Double

Remaining cost for a CBS-Expense combination

No

SummaryRemainingUnits

Double

Remaining Units for a CBS-Expense combination

No

Title

String

Project Title

No

uuu_object_id

Int

The resource Element id of the associated Resource

No



Legal Notices | Your Privacy Rights