The pre-activation procedures displayed in the following table can be executed outside a maintenance window (optional). Procedure completion time displayed here are estimates. The actual time taken may vary due to difference in database size, network configuration and loading, user experience, and user preparation.

Table 4-1 Pre-Feature Activation Overview

Procedure Elapsed Time (Hours:Minutes) Activity Feature Activation Preparation
  This Step Cum.  
System Topology Check 0:10-0:30 0:20-1:00
  • Verify network element configuration data.
  • Verify system group configuration data.
Perform Health Check 0:01-0:05 0:21-1:05
  • Verify DSR release
  • Verify server status
  • Log all current alarms