5 Feature Activation Execution Overview

The procedures shown in the following table are executed inside a single maintenance window. Procedure completion times shown here are estimates. Times may vary due to differences in database size, network configuration and loading, user experience, and user preparation.

Table 5-1 DCA Framework Activation Execution Overview

Procedure Elapsed Time (Hours:Minutes) Activity Feature Activation Preparation Impact
  This Step Cum.    
Perform Health Check - Pre-Feature Activation 0:01-0:05 0:01-0:05
  • Verify DSR release.
  • Verify proper DCA feature state.
  • Verify server status.
  • Log all current alarms.
None.
DCA Framework Activation 0:10-0:30 0:11-0:35
  • Log out of NOAM GUI.
  • SSH to active NO.
  • Change to the feature activation directory.
  • Execute the feature activation script.
  • Log into active NOAM and SOAM GUI.
  • Verify the DCA framework folder.
  • Close SSH connections to both NOAM.
DCA framework is activated on DSR.

The procedures shown in the following table are executed inside a single maintenance window. Procedure completion times shown here are estimates. Times may vary due to differences in database size, network configuration and loading, user experience, and user preparation.

Table 5-2 DCA Application Activation Execution Overview

Procedure Elapsed Time (Hours:Minutes) Activity Feature Activation Preparation Impact
  This Step Cum.    
DCA Application Activation 0:10-0:30 0:11-0:35
  • Log out of NOAM GUI.
  • SSH to active NO.
  • Change to the feature activation directory.
  • Execute the feature activation script.
  • Log into active NOAM and SOAM GUI.
  • Verify the DCA application folder.
  • Close SSH connections to both NOAMs.
DCA application is activated on DSR.