Activity Attributes (Units)

Assignment Attribute

Data Element

Calculation

Planned Total Units

uuu_P6PlannedTotalUnits

The planned units of work for the activity.

Actual Total Units

uuu_P6ActualTotalUnits

The exact number of units that have been expended on the selected activity.

Remaining Total Units

uuu_P6RemainingTotalUnits

The remaining units of work to be performed by the resource on the activity. Calculated as Planned Units minus Actual Units.

At Completion Total Units

uuu_P6AtCompletionTotalUnits

The sum of the actual units and remaining units for the resource assignment on the activity. Calculated as Actual Units plus Remaining Units.

See Also

Earned Value Management Attributes

Recost - Activity Attributes

Recost - Assignment Attributes

WBS Attributes

Activity Attributes (General)

Activity Attributes (Scheduling)

Activity Attributes (Cost)

Activity Attributes - Earned Value

Resource Attributes

Role Attributes

Rate Sheet - Rate Tab