Activity Attributes (Cost)
Assignment Attribute | Data Element | Calculation |
---|---|---|
Planned Total Cost |
| The expected total cost of the activity, consolidating costs of all assignments. |
Actual Total Cost |
| The actual non-overtime plus overtime cost for all the resource assignments of the activity. |
Remaining Total Cost |
| The remaining cost of all the resource assignments for the activity. |
At Completion Total Cost |
| The sum of the actual costs plus remaining costs for the resource assignment on the activity. Calculated as Actual Costs plus Remaining Costs. |
See Also
Earned Value Management Attributes
Recost - Assignment Attributes
Activity Attributes (Scheduling)
Activity Attributes - Earned Value