Activity Sheets Log (System Activity Sheet Properties Tabs)
In the Activity Sheets log, when you click and select the System Activity Sheet, the following properties tabs appear in the right pane:
- Mapped Projects tab
- Schedule tab
- History tab
The following describes the tabs listed above.
Mapped Projects tab
Toolbar options
- Assign Rate Sheet
To select Planning and Actuals specifications. You can select a rate sheet from the list and specify the project to which the rate sheet will be assigned (from the Project).
- Recost
To roll up the CBS costs (Cost Loaded), or to re-calculate all costs (Resource Loaded). It enables you to perform the cost calculations in an activity sheet, for type selected (that is, current schedule or baseline schedule).
- Refresh
To refresh the Mapped Projects tab log items.
- Find on Page
To find a particular project in the Mapped Projects tab log items.
Columns
- Project ID
- Project Name
- Project Type
- Project Start Date
- Data Date
- Schedule Type
- ETC Techniques
- Rate Sheet (Planning)
- Rate Sheet (Actuals)
Schedule tab
The Schedule tab enables you to:
- Set Frequency for
Set frequency for getting data or sending data (Set Frequency for).
- Frequency
Select the time frequency.
- Start Date
Set the start date.
- End Date
Set the end date.
History tab
The History tab enables you to see a history (the history of all events that have been performed across project sheets present in the activity sheet) of changes made on the system activity sheet.
Toolbar options
- Refresh
- Find on Page
Columns
- Action
- Requestor
- Initiated On
- Start Date
- End Date
- Status
When you click an item in the History tab, the History Details split screen appear at the bottom of the page which provides more details about the selected item.
In This Section
Mapped Projects Tab (System Activity Sheet)
Schedule Tab (System Activity Sheet)
History Tab (System Activity Sheet) and (Manual Activity Sheet)