Portfolio Budget Curve
The Portfolio Manager lets you pull the Baseline, or Forecast, data from more than one project or shell into the following Portfolio Budget curves:
- Approved Budget
- Original Budget
- Shared Budget
For an explanation of these options see Portfolio Manager Budget Curves.
The following topics explain how to add a Portfolio Budget curve for cash flow by:
- Project/Shell
- Summary CBS or CBS
- Commitment or Business Process (Commitments)
Notes: The procedures that follow:
- Assume that you have created your data sources.
- Describe how to add a curve type to an existing cash flow (Cash Flow log > Detail Level column > Project / Shell) that does not have a curve.
Related Topics
Adding Portfolio Budget Curve for Cash Flow by Project or Shell
Adding Portfolio Budget Curve for Cash Flow by Summary CBS or CBS
Adding Portfolio Budget Curve for Cash Flow by Business Process (Commitments)
Portfolio Budget Curve and Currency