Modifying Calendar Days on Global Calendars
P6 Setup Tasks > Application Settings and Global Enterprise Data in P6 EPPM > Working with Enterprise Data > About Calendars
Modify calendar days to account for work or nonwork days or hours that are different than the standard hours defined on the Standard Work Week tab.
To modify work or nonwork calendar days:
- Click Administration.
- On the Administration navigation bar, click Enterprise Data.
- On the Enterprise Data page, expand Global and click Global Calendars.
- On the Global Calendars page:
- Click on the calendar you want to modify.
- Click the Calendar tab.
- On the Calendar tab, click the Date list for a date and select Set to Standard or Nonwork.
- Click Save.
Related Topics
Setting Work Hours Per Time Period for Global Calendars
Configuring the Standard Work Week for Global Calendars
Setting the Default Global Calendar