Configuring Activity View Gantt Chart Bars
Configure the bar settings for the Gantt chart view on the Activities page.
To configure activity view bars:
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page:
- Click Customize View
- In the Manage Views dialog box, click the Bars tab.
- On the Bars tab click Configure.
- Select a theme to use a pre-configured set of colors for bars.
- Click a bar to configure it and then:
- Click the Bar Type list and choose one of the available bar types.
- Click the Height list and choose a height for the bar.
- Select the Show Progress option to chart progress, or actual work, along the Current Bar.
Select a Progress Color, a Bar Color, and a Progress Style to determine how progress will be shown on the bar.
- Select Show Critical to determine that the bar will display differently if the activity is critical.
Note: Click the Add menu and select Bar or Label to add a new bar or label. Select a bar or label and click to delete it.
- Click a label to configure it and then:
- In the Label Field list, select a field.
- In the Color field, select a text color.
- In the Height list, select a height.
Note: Click Preview to see how the bars and labels you have configured will look when shown with other bars.
- Click Apply.
Tips
- The Gantt chart only prints if it is displayed.
- A Late Bar does not display if the project has not been scheduled.
Related Topics
Configuring Activity View Columns
Configuring Activity View Grouping
Configuring Activity View Gantt Chart
Configuring Activity View Access
Converting Classic Views to Standard Views
Last Published Thursday, February 1, 2024