Configuring Activity View Access

Configure activity view access to define which users will have access to a particular view.

To configure access:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
    1. On the Activities page:
      • Click the Activity View list and select a multiple user activity view to configure.
      • Click Customize View.
    2. In the Manage Views dialog box, click the Access tab.
    3. On the Access tab, move users from the Available Users list to the Selected Users list to assign those users access to the view.

Tips

Related Topics

Configuring Activity Views

Configuring Activity View Columns

Configuring Activity View Grouping

Configuring Activity View Gantt Chart Bars

Configuring Activity View Gantt Chart

Configuring Activity Network

Converting Classic Views to Standard Views