Configuring Activity Resources

You can configure resource information for activities, including the Planned Units/Time, Proficiency, or Rate Type for a resource.

To configure activity resources:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page, select an activity and click the Assignments detail window.
  4. In the Assignments detail window:
    1. Select a resource.
    2. Add or remove the columns you need to configure to the detail window.
    3. Select an option or enter a value for each field.

Tips

Related Topics

About Resources

Assigning Resources to an Activity

Assigning Resources to Multiple Activities

Assigning Locations to Resources

Adding Activity Resource Estimates

Specifying Resource Assignment Rates

Assigning Resource Curves to Resource or Role Assignments from the Activities Page

Assigning Resources to Unstaffed Activities

About the Recalculate Assignment Costs Feature

Configuring Resource Leveling Options and Priorities

Leveling Project Resources

About the Check Resource Overallocation Service

About Resource Assignments

Showing or Hiding Columns in a Table



Last Published Thursday, February 1, 2024