Assigning Resources to Multiple Activities

Perform these steps to assign resources to multiple activities at one time.

To assign resources to multiple activities:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page, select the activities to which you want to assign resources.
    1. Click Row Actions and select Assign Resource.
    2. In the Select Resource dialog box select one or more resources.

      Note: Click Show Usage to show the usage chart for the selected resource and optionally change the Start and Finish fields to customize the visible portion of the usage chart. If you select more than one resource, the usage chart only shows usage for the first resource you selected.

    3. Click Select.

Tips

Related Topics

About Resources

Assigning Resources to an Activity

Configuring Activity Resources

Assigning Locations to Resources

Adding Activity Resource Estimates

Specifying Resource Assignment Rates

Assigning Resource Curves to Resource or Role Assignments from the Activities Page

Assigning Resources to Unstaffed Activities

About the Recalculate Assignment Costs Feature

Configuring Resource Leveling Options and Priorities

Leveling Project Resources

About the Check Resource Overallocation Service

About Resource Assignments



Last Published Thursday, February 1, 2024