Setting Work Hours Per Time Period for a Resource Calendar
Configure the work hours per time period settings to specify the default number of hours in a work period for a calendar.
To use this feature, select the Use assigned calendar to specify the number of work hours for each time period option, located on the Time Periods page of the Application Settings pane.
To set the number of work hours for each time period:
- Click Administration.
- On the Administration navigation bar, click Enterprise Data.
- On the Enterprise Data page, expand Resources and click Resource Calendars.
- On the Resource Calendars page:
- Click the calendar you want to modify.
- Click the Summary tab.
- In the Time Periods section, type an hour value in each field.
- Click Save.
Related Topics
Configuring Resource Calendars
Assigning a Base Calendar to a Resource Calendar
Assigning a Resource to a Resource Calendar
Configuring the Standard Work Week for Resource Calendars