Configuring the Standard Work Week for Resource Calendars

Configure the standard work week for the calendar to set the work and nonwork days and hours for a standard work week.

To configure the standard work week:

  1. Click Administration.
  2. On the Administration navigation bar, click Enterprise Data.
  3. On the Enterprise Data page, expand Resources and click Resource Calendars.
  4. On the Resource Calendars page:
    1. Click on the calendar you want to modify.
    2. Click the Standard Work Week tab.
  5. On the Standard Work Week tab:
    • Type the number of hours for each work day in the total hours field.
    • Or click and drag on the chart to create work periods for each work day.
  6. Click Save.

Tips

Related Topics

Configuring Resource Calendars

Assigning a Base Calendar to a Resource Calendar

Assigning a Resource to a Resource Calendar

Setting Work Hours Per Time Period for a Resource Calendar

Modifying Calendar Days

Changing the Calendar Type