Setting Overtime Policy

To set overtime policy, which enables users to enter overtime in their timesheets:

  1. Click Resources.
  2. On the Resources navigation bar, click Administration.
  3. On the Administration page, click the Resources tab.
  4. On the Resources tab, click the Settings detail window.
  5. In the Settings detail window, select the Overtime Allowed option.
  6. In the Overtime Factor field, type the overtime factor by which the resource's standard price is multiplied to determine the overtime price (standard price * overtime factor = overtime price).

    Note: In P6 and P6 Team Member, resources can enter overtime using separate overtime fields.

Related Topics

Resources

About Resources

Adding Resources

Assigning a Role to a Resource

Assigning a Resource Team to a Resource

Configuring Resource Settings

Assigning Calendars to Resources

Assigning Locations to Resources

Configuring Timesheet Reporting for Resources

Assigning Resource Codes

Assigning Resource Rates

Creating Import Templates for Importing Resources

Importing Resource Data

Deleting Resources



Last Published Wednesday, July 10, 2024