Global Calendars Page
Overview
Use this page to view or configure global calendar information and options.
Screen Elements
Add (Ins) button
Opens the Select Calendar to Copy dialog box.
Analyze Data Usage button
Analyzes the usage of the data items listed in the grid.
Full Screen
Expands the current work area so it fills the entire display.
Prints the Grid View.
Search
Searches the view or dialog box for data matching the criteria entered into the box.
Refresh
Refreshes the current screen with any new, updated, or removed data.
Row Actions menu
Add: Creates a new item.
Delete: Removes the selected item permanently.
Duplicate: Creates a new item as a copy of the selected item.
Set as Default Calendar: Sets the current calendar as the default calendar.
Calendar Name
Displays a list of all available calendars to view. This column is always visible on this page.
To see the following columns, click Analyze Data Usage.
Project Count field
The number of projects and baselines currently using the corresponding data item. The number reported in this column includes all projects and baselines in which the data item is assigned, regardless of your project access. To see a list of the projects and baselines using the corresponding data item, click the link. The list you see is restricted to those projects to which you have access.
Latest Update field
The most recent date that the corresponding data item was modified.
Latest Assignment Update field
The most recent date that the corresponding data item was assigned.
Latest Summarized Date field
The most recent time that a project or baseline using the corresponding data item was summarized.
Latest Published Date field
The most recent time that a project or baseline using the corresponding data item was published.
Latest Scheduled Date field
The most recent time that a project or baseline using the corresponding data item was scheduled.
Summary tab
See Summary Tab of the Global Calendars Page.
Calendar tab
See Calendar Tab of the Global Calendars Page.
Standard Work Week tab
See Standard Work Week Tab of the Global Calendars Page.
Used By tab
See Used By Tab of the Global Calendars Page.
Download
Enables you to download the data as an Excel file. For hierarchical data, the top level and any expanded levels are downloaded. For flat lists, all rows are downloaded.
Tips
- The project count includes assignments to projects, baselines, activities, and resources.
- You cannot delete the global default calendar.
- If you delete a calendar that is currently set as the project default calendar, or as the default calendar for a resource, or as the assigned calendar for an activity, you will be prompted to choose a replacement calendar for those assignments. Replacing the calendar for projects, resources, or activity assignments can cause the dates of those assignments to change.
- You need the Add/Edit/Delete Global Calendars or Add/Edit/Delete Resource Calendars security privileges to delete a calendar.
- When you are analyzing enterprise data usage, the Summary, Calendar, Standard Work Week, and Used By tabs are hidden. To bring the tabs back into view and hide the columns specific to analyzing enterprise data, select Refresh.
Getting Here
- Click Administration.
- On the Administration navigation bar, click Enterprise Data.
- On the Enterprise Data page, expand Global and click Global Calendars.
Related Topics
Setting Work Hours Per Time Period for Global Calendars
Configuring the Standard Work Week for Global Calendars
Modifying Calendar Days on Global Calendars
Setting the Default Global Calendar
Analyzing Enterprise Data Usage
Last Published Wednesday, July 10, 2024