Configuring the Resources Assignments Gantt Chart Bars

Configure the bar settings for the Gantt chart view on the Resources Assignments page. You can set features for up to three bars per assignment.

To configure the resource assignments Gantt chart bars:

  1. Click Resources.
  2. On the Resources navigation bar, click Assignments.
    1. On the Assignments page, click Customize View.
    2. Click Bars.
    3. On the Bars tab click Addand select Bar or Label.
    4. Select a bar or label.
    5. If you selected a bar:
      • Click the Bar Type list and choose one of the available bar types.

        Note: You can configure multiple bars. Set at least one bar to Current.

      • In the Height field, select the height for the bar.
      • In the Bar Color field, select a color.
      • Select Show Progress to show progress on the bar.
      • If you chose to show progress, select a Progress Color and Progress Style.
    6. If you selected a label:
      • In the Label Field field, select a bar label.
      • In the Height field, select the font size for the label.
      • In the Color field, select a color for the bar label.
      • Click Apply.

Related Topics

Working with Resource Assignments in the Gantt Chart

Viewing Resource Assignments in a Gantt Chart

Setting the Resources Detailed Assignments Gantt Chart Timescale