Recalculating Assignment Costs

Recalculate assignment costs to update price per time values on activities. This ensures that project costs reflect any updates.

To recalculate assignment costs:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page:
    1. Select an activity.
    2. Click Actions and select Recalculate Assignment Costs.
    3. In the Recalculate Assignment Costs dialog box:
    4. (Optional) Select the Synchronize overtime factor while recalculating costs option to synchronize the overtime factor defined for each resource when recalculating costs.
    5. Click Recalculate.

Tips

Related Topics

About Activities

Working with Activities

Creating Activities

Copying and Pasting Activities

Renumbering Activities

Configuring General Activity Information

Assigning Locations to Activities

About Activity Types

About WBS Summary Activities

About Suspending and Resuming Activities

Dissolving Activities

About the Activity Table and Grid View

About Activity Networks



Last Published Wednesday, July 10, 2024